Search This Blog

Monday, May 23, 2011

Pottery Road closed until September for road work


Pottery Road from Bayview Avenue to Broadview Avenue will be closed from May 24 to September 5 to complete a series of road, sidewalk and watermain improvements.

The work to be performed includes road reconstruction, with curbs, guiderails and retaining walls on Pottery Road, as well as a new sidewalk, watermain replacement, storm water upgrades, improvements to the Lower Don bike trail crossing at Pottery Road, and the relocation of various utilities.

"The City of Toronto continues to co-ordinate important road work with utility companies and other agencies to ensure that we keep disruptions to a minimum," said Councillor Denzil Minnan-Wong (Ward 34, Don Valley East), Chair of the City's Public Works and Infrastructure Committee.

During the closure there will be no through traffic on Pottery Road. However, local business access to Pottery Road will be maintained - with access provided from only one end of Pottery Road, either from Bayview Avenue or Broadview Avenue, depending on construction activities at different times. 

No comments:

Post a Comment

Top Headlines

U.S. Headlines

Department of Homeland Security News

USGS Earthquake ShakeMaps

Current Watches, Warnings and Advisories for Nevada Issued by the National Weather Service

Business Headlines

RoyaltyFreeMusic.com Music Reviews

Automobile RSS Feed

Buffalo, NY | Motion Center